Distributed energy resources; establishing provisions for electric generation behind the meter. Effective date.
What changed between versions
Added specific definitions for 'distributed energy resource', 'owner', 'operator', 'public utility', and 'retail electric supplier' to clarify who the law applies to.
Created exemptions from state and federal regulations, registration requirements, and fee payments for owners/operators who do not serve loads outside their ownership.
Established new requirements for constructing electric distribution lines in public rights-of-way, including posting performance bonds and providing 30-day written notice to utility providers.
Added procedures for handling objections to distribution line construction, requiring the Corporation Commission to conduct evidentiary hearings if a public utility objects.
Set the effective date of the act to November 1, 2025.