SB 713 Oklahoma Senate · 2025 Regular Session

Wind energy facilities; requiring newly established facilities to apply for certain technology system by certain date; providing for certain cost recovery. Effective date.

SB 713 requires new wind energy facilities in Oklahoma to apply for FAA- and FCC-approved light-mitigating technology systems (like aircraft detection lighting) before operations begin on or after January 1, 2026. Existing facilities without such systems must apply during repowering or when entering a new power offtake agreement, with installation required within 24 months of approval. Costs for installation, operation, and maintenance are the responsibility of facility owners/operators, though public utilities may seek rate recovery for these costs through the Corporation Commission. The bill also allows counties to issue revenue bonds to help cover these costs for pre-2026 facilities.
Bill status vetoed 4 of 5 stages cleared
Introduction
Feb 2025
Committee Review
May 2025
Senate Passage
May 2025
House Passage
May 2025
Vetoed
May 2025
Introduced Feb 3, 2025 Vetoed May 29, 2025
Maddy AI version diff · 7 comparisons

What changed between versions

Floor (House) Floor (Senate) · 3 edits
MINOR
The bill was amended to change the effective date from January 1, 2026 to November 1, 2025, and removed references to the Federal Communications Commission (FCC) for frequency licensing and antenna registration requirements, leaving only the Federal Aviation Administration (FAA) as the required approval authority for light-mitigating technology systems.
Scope change
The bill's applicability timeline was accelerated by approximately two months, and the regulatory scope was narrowed by removing FCC involvement in the compliance process for wind energy facilities.
TIMELINE

The effective date for the act was changed from January 1, 2026 to November 1, 2025, requiring wind energy facilities to comply with new light-mitigating technology requirements earlier than originally planned.

REQUIREMENT

References to the Federal Communications Commission (FCC) for frequency licensing and antenna structure registration were removed, simplifying the approval process to only require FAA approval for light-mitigating technology systems.

DEFINITION

Minor formatting and line break adjustments were made to the definitions section, though the substantive definitions of terms like 'wind energy facility' and 'light-mitigating technology system' remained unchanged.

Floor votes

How they voted

This bill passed the Senate by voice vote (no roll call recorded).
Full legislative history

Actions timeline

Total actions
33
Key actions
11
Committee
7
May 29, 2025
Introduced
Filed with Secretary of State
upper
May 29, 2025
Vetoed
Veto overridden: Ayes: 68 Nays: 17
lower
May 29, 2025
Vetoed
Veto override message received
lower
May 29, 2025
Vetoed
Veto overridden: Ayes: 32 Nays: 15
upper
May 27, 2025
Vetoed
Vetoed 05/27/2025
upper
May 20, 2025
Committee
Referred for enrollment
upper
May 20, 2025
Upper · Passed
Measure passed: Ayes: 30 Nays: 16
upper
May 20, 2025
Upper · Passed
HAs adopted
upper
May 5, 2025
Lower · Passed
Engrossed, signed, to Senate
lower
May 1, 2025
Committee
Referred for engrossment
lower
May 1, 2025
Lower · Passed
Third Reading, Measure passed: Ayes: 64 Nays: 16
lower
Apr 23, 2025
Lower · Passed
CR; Do Pass, amended by committee substitute Energy and Natural Resources Oversight Committee
lower
Apr 3, 2025
Lower · Passed
Policy recommendation to the Energy and Natural Resources Oversight committee; Do Pass Energy
lower
Apr 1, 2025
Committee
Referred to Energy
lower
Mar 26, 2025
Introduced
First Reading
lower
Mar 26, 2025
Upper · Passed
Engrossed to House
upper
Mar 25, 2025
Committee
Referred for engrossment
upper
Mar 25, 2025
Upper · Passed
Measure passed: Ayes: 28 Nays: 17
upper
Feb 13, 2025
Upper · Passed
Reported Do Pass Energy committee; CR filed
upper
Feb 3, 2025
Introduced
First Reading
upper
2 primary · 0 co-sponsors

Sponsors