Public works: prevailing wages: access to records.
What changed between versions
The scope was broadened from 'any public works project subject to the requirements of this chapter' to 'any work, subject to the prevailing wage requirements of this chapter,' removing the explicit 'public works project' limitation.
A separate subdivision (b) that explicitly extended the record-keeping requirement to development projects that include public work (even if not entirely a public work) was removed. The broader scope is now achieved through the revised language in subdivision (a).
The compliance deadline for owners or developers to produce records upon written request was extended from 10 calendar days to 30 calendar days.
The deadline for a Taft-Hartley trust fund or joint labor-management committee to file a complaint with the Division of Labor Standards Enforcement after non-compliance was extended from 10 calendar days to 30 calendar days.
Complaint filing by a trust fund or joint labor-management committee changed from mandatory ('shall submit') to permissive ('may submit'), giving these entities discretion over whether to escalate non-compliance.
The penalty trigger was narrowed. Previously, penalties could be imposed if the Division determined the owner failed to provide records or failed to comply with various subdivisions. Now penalties are only triggered when the Division receives a complaint from a trust fund or committee and the owner fails to comply with the Division's subsequent written request within 10 days.
The requirement that the Division of Labor Standards Enforcement 'shall promptly investigate any complaints' was removed.
Cross-reference corrections were made: 'paragraph (2) (5)' corrected to 'paragraph (5)' and 'paragraphs (1) and (3) through (4)' corrected to 'paragraphs (1) through (4).' The Information Practices Act citation was cleaned up by removing a redundant 'Title 1.8' reference.