SB 700 California Senate · 2017-2018 Regular Session

Self-generation incentive program.

Summary
Existing law requires the Public Utilities Commission (PUC) to open a proceeding to determine appropriate targets, if any, for each load-serving entity, as defined, to procure viable and cost-effective energy storage systems to be achieved by December 31, 2015, and December 31, 2020. If determined to be appropriate, the commission is required to adopt the procurement targets, by October 1, 2013, and to reevaluate the determinations not less than once every 3 years. Existing law excludes an electrical corporation that has 60,000 or fewer customer accounts within California from these requirements. In response to a requirement to adopt initiatives on or before March 7, 2001, to reduce demand for electricity and reduce load during peak demand periods, including differential incentives for renewable or super clean distributed generation resources, the PUC adopted decisions establishing a self-generation incentive program. Existing law authorizes the PUC to authorize the annual collection of not more than double the amount authorized for the self-generation incentive program in the 2008 calendar year, through December 31, 2019. Existing law requires the PUC to require electrical corporations to administer the program for distributed energy resources established pursuant to the above-described law until January 1, 2021, and to separately administer solar technologies pursuant to the California Solar Initiative. Existing law requires the PUC to provide repayment of all unallocated funds collected for the self-generation incentive program on January 1, 2021, to reduce ratepayer costs. Existing law requires the PUC, on or before July 1, 2015, to update the factor for avoided emissions of greenhouse gases, as provided, to determine eligibility for participation in the program. This bill would extend the collection for the self-generation incentive program to December 31, 2024, and the administration of the program to January 1, 2026. The bill would require the commission to adopt requirements for energy storage systems to ensure that eligible energy storage systems reduce the emissions of greenhouse gases. The bill would specify that generation technologies using nonrenewable fuels are not eligible for incentives under the program on and after January 1, 2020. Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime. Because a violation of an order or decision of the commission implementing the requirements of this bill would be a crime, the bill would impose a state-mandated local program by creating a new crime. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.
Bill status signed all 5 stages cleared
Introduction
Feb 2017
Committee Review
Aug 2018
Senate Passage
May 2017
Assembly Passage
Aug 2018
Signed into Law
Sep 2018
Introduced Feb 17, 2017 Signed Sep 27, 2018
Floor votes · Senate Aug 30, 2018 · Assembly Aug 29, 2018

How they voted

2010
Passed · 2 other
Total votes 32
Aug 30, 2018
D Democratic21
19 Yea 2
90% Yea
R Republican11
1 Yea 10 Nay
90% Nay
Vote distribution
All Yea All Nay Mixed No data
Full legislative history

Actions timeline

Total actions
39
Key actions
13
Committee
10
Amendments
4
Sep 27, 2018
Signed into law
Approved by the Governor.
legislature
Aug 30, 2018
Senate · Passed
Senate Vote: pass (20-10-2)
senate
Aug 30, 2018
Upper · Passed
Assembly amendments concurred in. (Ayes 25. Noes 12. Page 6023.) Ordered to engrossing and enrolling.
upper
Aug 29, 2018
Assembly · Passed
Assembly Vote: pass (51-16-3)
assembly
Aug 29, 2018
Introduced
In Senate. Concurrence in Assembly amendments pending.
upper
Aug 24, 2018
Lower · Passed
Read third time and amended.
lower
Aug 16, 2018
Lower · Passed
From committee: Do pass as amended. (Ayes 12. Noes 0.) (August 16).
lower
Jun 26, 2018
Lower · Passed
Read second time and amended. Re-referred to Com. on APPR.
lower
Jun 25, 2018
Lower · Passed
From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 1.) (June 20).
lower
Jul 12, 2017
Lower · Passed
July 12 hearing postponed by committee.
lower
Jun 15, 2017
Committee
Referred to Com. on U. & E.
lower
May 26, 2017
Upper · Passed
From committee: Do pass as amended. (Ayes 5. Noes 2. Page 1189.) (May 25).
upper
May 2, 2017
Upper · Passed
Read second time and amended. Re-referred to Com. on APPR.
upper
May 1, 2017
Upper · Passed
From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 7. Noes 2. Page 806.) (April 24).
upper
Apr 6, 2017
Upper · Passed
April 18 hearing postponed by committee.
upper
Mar 29, 2017
Committee
Re-referred to Com. on E., U. & C.
upper
Mar 9, 2017
Committee
Referred to Com. on RLS.
upper
Feb 17, 2017
Introduced
Introduced. Read first time. To Com. on RLS. for assignment. To print.
upper
1 primary · 0 co-sponsors

Sponsors

Role
Legislator
Party
State
District
P
Photo of Scott Wiener
Scott Wiener
DDemocratic
CA
11