Industrial, wind and solar projects-hearing deadline.
What changed between versions
Extended the deadline for county boards to hold public hearings from 45-60 days to 45-90 days after determining an application is complete.
Extended the deadline for county boards to issue permit decisions from 45-60 days to 60 days after hearing completion.
Extended the time for applicants to provide additional information for incomplete applications from 30-60 days to 45 days.
Extended the deadline for the Department of Environmental Quality to act on permit applications from 90-120 days to 120 days after receipt.
Added requirement for the director to notify applicants of specific deficiencies within 30 days of determining an application is incomplete.
Changed effective date to January 1, 2026, with applicability to applications submitted on or after that date.