Relating to energy facilities.
What changed between versions
Added detailed notice requirements for public hearings including descriptions of the facility, contact information, and statements about inspection availability.
Changed the timing of when issues must be raised from before the proposed order to before the final public hearing.
Removed the summary section and editorial notes that were present in the A-Engrossed version but not in the enrolled version.
Established a 12-month deadline for the Energy Facility Siting Council to conclude contested cases and issue final orders.
Created specific approval timelines for different facility types: 24 months for nuclear and large thermal plants, 9 months for combustion turbines and geothermal plants, 6 months for expansions, and 12 months for other facilities.
Added provisions for expedited processing of applications for facilities under 100 megawatts with no notice of intent required.