HB 1095 North Dakota House · 67th Legislative Assembly (2021-2022)

Relating to the siting of a repowered wind conversion facility that has not previously been issued a certificate of site compatibility; and to amend and reenact sections 49‑22‑03 and 49‑22‑16.4 of the North Dakota Century Code, relating to the definition of repower for a wind facility and waivers or extensions for light mitigation technology systems.

Bill status signed all 5 stages cleared
Introduction
Jan 2021
Committee Review
Mar 2021
House Passage
Jan 2021
Senate Passage
Mar 2021
Signed into Law
Mar 2021
Introduced Jan 5, 2021 Signed Mar 19, 2021
Floor votes · Senate Mar 9, 2021 · House Jan 15, 2021

How they voted

45–1
Passed · 1 other
Total votes 47
Mar 9, 2021
D Democratic7
6 Yea 1 Nay
85% Yea
R Republican40
39 Yea 1
97% Yea
Vote distribution
All Yea All Nay Mixed No data
Full legislative history

Actions timeline

Total actions
15
Key actions
7
Committee
4
Mar 22, 2021
Introduced
Filed with Secretary Of State 03/18
legislature
Mar 19, 2021
Signed into law
Signed by Governor 03/17
executive
Mar 9, 2021
Upper · Passed
Second reading, passed, yeas 45 nays 1
upper
Mar 8, 2021
Upper · Passed
Reported back, do pass, place on calendar 6 0 0
upper
Mar 4, 2021
Upper · Passed
Committee Hearing 09:00
upper
Feb 3, 2021
Introduced
Introduced, first reading, referred Energy and Natural Resources Committee
upper
Jan 15, 2021
Lower · Passed
Second reading, passed, yeas 79 nays 11
lower
Jan 14, 2021
Lower · Passed
Reported back, do pass, place on calendar 10 4 0
lower
Jan 14, 2021
Lower · Passed
Committee Hearing 11:00
lower
Jan 5, 2021
Introduced
Introduced, first reading, referred Energy and Natural Resources Committee
lower
0 primary · 0 co-sponsors

Sponsors

No sponsor information available.