S 731: Requires electric public utilities to develop and apply special rules for large load customers to protect non-large load customers from increased costs.*
S 731 requires New Jersey electric utilities to create special pricing plans for large data centers (defined as facilities with 100+ megawatts monthly demand) to protect regular electricity customers from cost increases. The bill mandates that these plans must prevent non-data center ratepayers from bearing costs from data centers' high energy use and incentivize data centers to improve energy efficiency, including using waste heat. Utilities must submit these plans to the Board of Public Utilities within 180 days, and the rules will take effect one year after the bill passes. Key requirements include data centers committing to 85% service levels for 10 years, proving project uniqueness, and providing financial guarantees to cover potential cost overruns if they reduce service.