UTILITIES-INTERCONNECTIONS
Summary
Amends the Public Utilities Act. Sets forth procedures for the processing of interconnection requests from applicants for distributed renewable generation projects on public school land. Provides that, for all net metering credits or other credits owed to a customer who has elected to install a distributed renewable generation project on public school land, all credits intended for the benefit of the consumer must be credited by the public utility or retail energy supplier within 90 days after the public utility or retail energy supplier determines that the criteria for the credit have been met. Provides that the Illinois Commerce Commission shall adopt revisions to its standards for the interconnection of eligible renewable generating equipment and net metering credit rules to conform with the requirements of the provisions of the amendatory Act. In provisions concerning customer self-generation of electricity, provides that, for distributed renewable generation projects on public school land, any fees for interconnection applications charged by the electric cooperative or municipal system must be substantially similar to the fees charged by public utilities for the interconnection of the same or similar projects and must not exceed 150% of the cost of the base interconnection fees of the other public utilities. Effective immediately.
Bill status
signed
all 5 stages cleared
Introduction
May 2026
Committee Review
May 2026
Senate Passage
May 2026
House Passage
May 2026
Signed into Law
Jul 2026
Introduced May 20, 2026
Signed Jul 10, 2026
Maddy AI version diff · 2 comparisons
What changed between versions
Engrossed
→
Enrolled
·
3 edits
·
Jul 10, 2026
MINOR
The bill transitioned from its 'Engrossed' version to the final 'Enrolled' version ready for signing. The primary substantive change involves a technical correction to the metering requirements for customers on demand-based pricing, specifying that a 'dual channel meter' is required to measure electricity flow in both directions. Additionally, the text was cleaned up to remove redundant page headers and ensure consistent formatting throughout the document.
TECHNICAL
Corrected the metering specification for customers on hourly pricing to require a 'dual channel meter' capable of measuring electricity flow in both directions.
Removed redundant page headers and footer markers that appeared in the middle of the text in the previous version.
Adjusted punctuation and spacing in the definitions section to ensure consistent formatting.
Floor votes · Senate May 20, 2026 · House May 27, 2026
How they voted
55–0
Passed · 3 other
Total votes 58
May 20, 2026
D
Democratic39
97% Yea
R
Republican19
89% Yea
Vote distribution
All Yea
All Nay
Mixed
No data
Full legislative history
Actions timeline
Total actions
52
Key actions
11
Committee
13
Amendments
10
Jul 10, 2026
Signed into law
Governor Approved
upper
May 31, 2026
Upper · Passed
Passed Both Houses
upper
May 31, 2026
Introduced
House Floor Amendment No. 1 Senate Concurs 058-000-000
upper
May 29, 2026
Introduced
House Floor Amendment No. 1 Motion To Concur Recommended Do Adopt Energy and Public Utilities; 011-000-000
upper
May 28, 2026
Committee
House Floor Amendment No. 1 Motion to Concur Assignments Referred to Energy and Public Utilities
upper
May 28, 2026
Committee
House Floor Amendment No. 1 Motion to Concur Referred to Assignments
upper
May 28, 2026
Introduced
Placed on Calendar Order of Concurrence House Amendment(s) 1 - May 29, 2026
upper
May 28, 2026
Introduced
Secretary's Desk - Concurrence House Amendment(s) 1
upper
May 27, 2026
Lower · Passed
Third Reading - Short Debate - Passed 109-000-000
lower
May 27, 2026
Lower · Passed
House Floor Amendment No. 1 Adopted by Voice Vote
lower
May 21, 2026
Lower · Passed
House Floor Amendment No. 1 Recommends Be Adopted Rules Committee; 003-002-000
lower
May 21, 2026
Committee
House Floor Amendment No. 1 Referred to Rules Committee
lower
May 21, 2026
Introduced
House Floor Amendment No. 1 Filed with Clerk by Rep. Jay Hoffman
lower
May 21, 2026
Lower · Passed
Do Pass / Short Debate Public Utilities Committee; 019-000-000
lower
May 21, 2026
Lower · Passed
Motion Filed to Suspend Rule 21 Public Utilities Committee; Rep. Ann M. Williams
lower
May 21, 2026
Lower · Passed
Committee/Final Action Deadline Extended-9(b) May 31, 2026
lower
May 21, 2026
Committee
Assigned to Public Utilities Committee
lower
May 20, 2026
Committee
Referred to Rules Committee
lower
May 20, 2026
Introduced
Arrived in House
lower
May 20, 2026
Upper · Passed
Third Reading - Passed; 056-000-000
upper
May 20, 2026
Upper · Passed
Senate Floor Amendment No. 1 Adopted; Cunningham
upper
May 14, 2026
Introduced
Senate Floor Amendment No. 1 Recommend Do Adopt Energy and Public Utilities; 012-000-000
upper
May 12, 2026
Introduced
Senate Floor Amendment No. 1 Assignments Refers to Energy and Public Utilities
upper
May 6, 2026
Committee
Senate Floor Amendment No. 1 Referred to Assignments
upper
May 6, 2026
Introduced
Senate Floor Amendment No. 1 Filed with Secretary by Sen. Bill Cunningham
upper
Mar 12, 2026
Upper · Passed
Do Pass Energy and Public Utilities; 013-000-000
upper
Feb 17, 2026
Committee
Assigned to Energy and Public Utilities
upper
Feb 3, 2026
Committee
Referred to Assignments
upper
2 primary · 2 co-sponsors
Sponsors
Role
Legislator
Party
State
District
P
Bill Cunningham
DDemocratic
P
Jay Hoffman
DDemocratic
Co
Chris Balkema
RRepublican
Co
Javier Cervantes
DDemocratic
Ask Maddy
·
AI policy assistant
Ask Maddy about SB 3273
Scope: IL
Hi! I can help you understand SB 3273. What would you like to know?
Try one of these
i
Maddy answers using official bill text and legislative records. Always verify before sharing.
Sources cited inline