SB 743 Hawaii Senate · 2021 Regular Session

RELATING TO PERMIT PROCESSING.

Summary
Beginning July 1, 2021, requires the State or an appropriate county agency to approve, approve with modification, or disapprove an application for a permit necessary for the development, pre-development, construction, or substantial rehabilitation of a project within sixty-five days of submission. Provides for automatic permit approval if the State or respective county agency does not make a timely decision on the application.
Bill status in committee 1 of 4 stages cleared
Introduction
Jan 2021
Committee Review
Floor Vote
Governor
Introduced Jan 22, 2021 Last action Jan 27, 2021
Floor votes

How they voted

No floor votes recorded yet.
Full legislative history

Actions timeline

Total actions
3
Key actions
0
Committee
1
Jan 27, 2021
Committee
Referred to WTL/PSM, JDC.
upper
Jan 22, 2021
Introduced
Introduced.
upper
3 primary · 0 co-sponsors

Sponsors