AN ACT CONCERNING GRID-ENHANCING TECHNOLOGIES.
What changed between versions
The original task force to study transmission infrastructure was removed entirely.
Utility companies must now design at least two project alternatives: one using advanced conductors and one using grid-enhancing or nontransmission technologies.
Annual reporting requirements added for utilities to file construction schedules, plain-language descriptions, and project cost data with the Public Utilities Regulatory Authority.
New effective date set for October 1, 2025, with reporting requirements beginning January 15, 2026.
New definitions added for advanced conductors, grid-enhancing technology, nontransmission alternatives, and other technical terms.
The Connecticut Siting Council must give preference to cost-effective project alternatives using grid-enhancing technologies when reviewing applications.